Customer Case Blood components production was organized in the basement of the building and was extremally manual. Production started to grow and it has become necessary to scale up facility and change the way they work to meet modern requirements. CoolSystems – implementation of the system We designed and built up from scratch new wing… View Article
- Customer Case
Blood components production was organized in the basement of the building and was extremally manual. Production started to grow and it has become necessary to scale up facility and change the way they work to meet modern requirements. - CoolSystems – implementation of the system
We designed and built up from scratch new wing of a building with the size of 1500 m2. The building was adapted to the production and dispatch of blood components. The heat generated by cooling systems is used to power technical equipment of the building.
- Project results
Three floors Automatic Plasma Storage has become a heart of new building and new blood component production process. It has capacity of 80,000 containers and average access time is 1 min. Innovative solution minimized the number of refrigeration systems and the consumption of electricity has been reduced by 20kW. Now the building is self-sufficient in terms of heating and hot water.